Hello All,
I have e question about the sequence and order of execution of pressure testing with paint according to PD5500.
In our company we have a design of a headerbox of an air cooled cooler that can only be hydrotested after applying paint. Otherwise we have to change the design and make a lot of extra effort and increase of costs to produce otherwise.
Can somebody inform me if this is allowed by PD5500? Or depending on selected category?
I have searched the specification without finding the answer.
I have searched codes as API661, ASME VIII div 1 (non lethal) where it is allowed to do so. Other codes like Rtod, EN 13445 and AD2000 will not allow, or in special circumstances. Overall knowing that it's manufacturer own responsibility.
Before asking our NoBo i'm hoping to get the right answer here.
Can anyone provide me with the correct answer?
Thanks in advance,
EuroWeld
I have e question about the sequence and order of execution of pressure testing with paint according to PD5500.
In our company we have a design of a headerbox of an air cooled cooler that can only be hydrotested after applying paint. Otherwise we have to change the design and make a lot of extra effort and increase of costs to produce otherwise.
Can somebody inform me if this is allowed by PD5500? Or depending on selected category?
I have searched the specification without finding the answer.
I have searched codes as API661, ASME VIII div 1 (non lethal) where it is allowed to do so. Other codes like Rtod, EN 13445 and AD2000 will not allow, or in special circumstances. Overall knowing that it's manufacturer own responsibility.
Before asking our NoBo i'm hoping to get the right answer here.
Can anyone provide me with the correct answer?
Thanks in advance,
EuroWeld