Some further context
- the footing holes / works have been fully engineered
- I am performing non structural demolition, and digging the required 2 footing holes
- I have commenced the work I committed to doing before the builder commences - simply, digging a footing hole per the engineering specification
- the builder will validate, building surveyor inspect, prior to concrete pour
My concern is that in a typical scenario, the duration between digging the hole, inspection and concrete would be substantially shorter than what i’ve done - am I now at risk of the existing strip footing being undermined? Only questioning as we’ve dug right next to it, per the proposed location of the new pad, at a depth lower than the existing, again per the engineering.. Should I be filing it back in with dirt, compacting and waiting until the day it’s actually required? Once the concrete is in, it’s not an issue, the concern is the extended period prior.
Thanks