Civilling
Civil/Environmental
- Nov 9, 2016
- 8
I have elementary questions about rebar on center spacing specified on drawings. If I have a new 10' x 2.5' x 1' height slab and have determined I need a 13#4 longitudinal bars and 4#4 transverse bars per temperature and shrinkage, how do I specify this on drawings? Would I specify #4 at 9" on center, each way, 3" clear typical? Does the contractor read that as 9" maximum on center spacing or exact spacing? i.e. they measure the 2.5' direction, they would lay 4#4's because the max spacing is 9", vs could they potentially lay 3#4s exactly at 9" on center with more clear cover?