Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations TugboatEng on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Need to assign costs to a pseudo hammock activity

Status
Not open for further replies.

airduds

Electrical
Joined
Jun 22, 2006
Messages
2
Location
US
I need to tie a support activity to a change of tasks such that it acts like a hammock - that it's duration mimics that of the work activities. There is a fixed cost per hour associated with the support activity that I would like to be able to show.

Is this something I'm going to have to manage manually?

Primavera P3 3.1 sp2

Thanks for your help
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top