Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Multilevel Residential Basement Retaining Wall Bracing

Status
Not open for further replies.

jdgengineer

Structural
Joined
Dec 1, 2011
Messages
767
Location
US
We have another project with a multilevel basement that I was hoping to get some ideas on. We are in the process of our schematic design stage. I know I started a thread awhile back with similar questions, but wanted to revisit it as our layout is a little different and I felt we were somewhat reinventing the wheel for something that I imagine should be fairly common.

See attached for general layout of the proposed lower basement, mezzanine basement level, and ground floor level. Our initial thought is a thick concrete matslab for the basement foundation (geotech recommendations) and concrete topped pandeck for the mezzanine and ground floor level. The 2nd floor and roof level would be mainly wood framed with steel beams as necessary for the longer spans.

It is standard practice in our area to design single story retaining walls as cantilevered walls from the basement matslab (i.e. not pinned at the floor) and require that backfilling be completed prior to framing the floor. However, with the depth of the basement I don't think that will work well for us and instead will need to brace at the floor levels. In looking at the layout of the mezzanine level, I think there are two many openings to consider this an effective bracing level. Therefore, we are planning on designing the wall to clear span from the lowest level to the ground floor (~25'). To make matters worse the local building requirements for this project do not allow the basement wall to be drained and therefore we have to design for undrained conditions. Our geotechnical report recommends 85 PCF + 10H uniform for the non-yielding condition.

Running fairly quick numbers, I obtain a service level reaction of approximately 11k / ft at the ground floor level assuming I have a pinned-pinned connection for the wall. With a fixed-pinned I have a service level reaction of approximately 7 k / ft. Our wall is looking to be about 30" thick to resist shear and bending moment at the base.

1) How are walls like this commonly braced at the top for such a high reaction per foot? Part of me wants to make the mezzanine and ground floor level cast in place concrete in lieu of pandeck but I know the contractor really wouldn't like that.

2) On our past multi-level basement we were able to strut pretty effectively across the basement with the metal deck and attempted to design the topping slab (6" thick) for the compression force. In our case here, I think the geometry of the basement and openings due to lightwells and stairs makes this more difficult. Therefore, if we went with pandeck we were thinking of adding steel beams at say 10' o.c. to try and brace the wall. An initial thought was to cut in bearing seats in the wall for the steel beams and weld on end plates which could then be grouted tight to the wall to transfer all the lateral reactions in bearing instead of bolt shear.

3) With such a thick wall, how effective to you think fixity at the base would be? Our matslab would likely be 24-36" thick.

Any thoughts on a schematic structural solution?
 
 http://files.engineering.com/getfile.aspx?folder=77342e3f-286b-44c8-9931-bc2399237702&file=Multilevel_Basement.pdf
Different areas of the wall look to be supported by the floors ( I assume the mezzanine level has the move room) but the two story spaces are what they are. You may be able to span the wall horizontally, or utilize two way action, to help thin up the wall, but the loads get into each level either way. If its getting so tough, it may be worth a full FEM model to see how it will behave overall. with all the return walls and short faces, the two way action may help quite a bit.
 
1) Not sure there is a "commonly" for something like this. I think that external, top of wall concrete girt beams could help in many instances. Where those beams wouldn't reach return walls, I'd consider strutting across to the other side with a concrete or steel beam.

2) Said pretty much everything I can think of in that previous thread.

3) I think that a high degree of fixity would be pretty easy to achieve at those proportions. Closing joints perform well and these are those.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top