Apr 1, 2004 #1 rkadan Computer Joined Apr 1, 2004 Messages 1 Location US I am trying to do the following steps 1. Open MS Project 2. Create a task 3. Make the duration as 1 day 4. Go to the right plane 5. Drag the task to make it for 2 days 6. Now the task duration column shows 1.88 rather than 2 days.Why? Please help.
I am trying to do the following steps 1. Open MS Project 2. Create a task 3. Make the duration as 1 day 4. Go to the right plane 5. Drag the task to make it for 2 days 6. Now the task duration column shows 1.88 rather than 2 days.Why? Please help.
Apr 1, 2004 #2 IRstuff Aerospace Joined Jun 3, 2002 Messages 44,896 Location US The only way that happens on my setup is if you have the minimum time scale set for hours and you've actually got 1 day and 7 hours. When smallest timescale is set to days, the smallest change I can get is 0.5 days TTFN Upvote 0 Downvote
The only way that happens on my setup is if you have the minimum time scale set for hours and you've actually got 1 day and 7 hours. When smallest timescale is set to days, the smallest change I can get is 0.5 days TTFN