Minimum Pile Spacing Before Group Effect on Lateral Capacity 1

Status
Not open for further replies.

BigEasyGeoSleuth

Geotechnical
Dec 3, 2006
14
What are you geotechs using for the minimum pile spacing before group effect needs to be considered for lateral load capacity for drilled shaft groups? I have seen 6D.

For Auger Cast Pile groups? (may be less due to the auger providing lateral support??)
 
Replies continue below

Recommended for you

I think the latest AASHTO code uses 5D as the limit.
 
Poulos and Davis have a good discussion on this in "Pile Foundation Analysis and Design".
 