I have a two story building with a balloon frame, 22' high. The wall is attached solidly to the main building and has a height:width ratio of about 1:1.15
The tile roof anchors the wall against uplift and calculations do not require a hold down.
However, is there a minimum requirement for hold downs?
I came on to this job after the architect (who calc'd everything himself" was told he needed engineering (he does- the house is very irregular and in seismic zone 4)
This home construction permit was issued under UBC97.