jamesbanda
Chemical
- Sep 21, 2004
- 223
Dear all,
i understand the risk of structured packing fires during turnarounds etc. that a spark could be a major risk.
Is this the same case for a new install of stuctured packing into a clean column on a new plant.?
and is the risk the same as the packing is being stored?
ie do we need to be carefull installing the packing in a constuction site?
i understand the risk of structured packing fires during turnarounds etc. that a spark could be a major risk.
Is this the same case for a new install of stuctured packing into a clean column on a new plant.?
and is the risk the same as the packing is being stored?
ie do we need to be carefull installing the packing in a constuction site?