The maximum pour size is determined by site logistics how many concrete trucks the contractor can get to site before they need to stop. The maximum I've experienced is 1200m3 in a day
For tendon lengths, about 30m for a band beam, 40m for a slab tendon. If you use double live end tendons you can go about double that, but pour sizes may become impractical. Minimum tendon length of about 6m, otherwise losses from wedge draw in become excessive.