livewire9
Structural
- Aug 4, 2010
- 49
I am on a team designing a substation layout. We are trying to achieve a compact, economical arrangement. It has been proposed that a 3-transformer bay (or more) layout could be achieved with a drive path around the equipment; imagine an oval track around a small sub. I think it could be problematic for maintenance or replacement of the inside 138/12.5kV transformer(s) using a crane. Isn't it preferable to jack and slide xfmrs onto foundation pads? Is it a good design to risk having a transformer being lifted over other equipment (e.g. switchgear and bus) for the sake of saving a little bit of real estate?