dcfrush
Petroleum
- May 14, 2007
- 9
My refinery has always done this in the past but I'm not sure it is necessary (small bore piping <2" and service with H2S >50 ppm in water phase). Would it be sufficient to maintain a preheat of ~200 degF, use E7018 low hydrogen electrodes, and follow up with a PT 48 hours after welding, assuming there was no history of cracking in the service or hydrogen blisters?
Thanks in advance,
- David
Thanks in advance,
- David