Lion06
Structural
- Nov 17, 2006
- 4,238
I've always been taught that it is and to minimize field welding on the documents. What confuses me, however, is that if it's really that much extra cost to the erector why is so much unnecessary weld laid in the field?
I obviously only have a few years under my belt, but I've seen so muh extra field welding done that it makes me question the premise that it's cost prohibitive. On one recent project we had HSS shear connections thy consisted of a seat with a top angle. The top angle was for stability only so we called out for only the tips to be welded to the HSS. When on a site visit, however, they had everything welded up! The angle was welded all the way around ( to HSS and to the column) and the HSS
was welded all around directly to the column!
This happened in quite a few places. Why would they lay weld that is not called for if it's that expensive and coming out of their own pocket?
I obviously only have a few years under my belt, but I've seen so muh extra field welding done that it makes me question the premise that it's cost prohibitive. On one recent project we had HSS shear connections thy consisted of a seat with a top angle. The top angle was for stability only so we called out for only the tips to be welded to the HSS. When on a site visit, however, they had everything welded up! The angle was welded all the way around ( to HSS and to the column) and the HSS
was welded all around directly to the column!
This happened in quite a few places. Why would they lay weld that is not called for if it's that expensive and coming out of their own pocket?