Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

interface of concrete pours

Status
Not open for further replies.

jxzohio

Geotechnical
Jul 16, 2005
12
There is a new construction house which I want to purchase. But on the basement walls, I found a long horizontal line (quite obvious) which I believe is due to different concrete pours. The line is about 25 feet long and 3 to 4 feet above basement floor. I am quite concerned about the possible leakage in the future through the interface of different concrete pours. Is this a potential problem in the future? Does the interface undermine the integrity of the basement wall? Thanks.
 
Replies continue below

Recommended for you

If the construction joint was constructed correctly there should be no need for worry.

However since there is no real need for a construction joint at the location you describe except that they ran into trouble during the pour (i.e. weather, equipment breakdown or concrete delivery problems) I’d assume the worst and that it was constructed in a hurry and might not be done correctly.

Unfortunately no easy way to determine how it was made.

Any sign of leakage or water penetration along the joint? Is it straight and regular or irregular?

Rick Kitson MBA P.Eng

Construction Project Management
From conception to completion
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor