majmaz
Structural
- Nov 3, 2009
- 8
In a mass housing project that includes of 4-story buildings with light gauge system(LSF),it is planning to assemble structure of each story (wall frames + joists and metal sheet of ceiling) on the floor next to the building. Then it will be lifted and installed at story level by crane.
Off course temporary horizontal bracing will be provided at bottom level of wall frames to prevent deformation at lifting time. Plan of buildings is rectangle (30'x25') and staircase is installed separately too.
Does anybody have experiences or suggestion for mentioned method of construction?
Off course temporary horizontal bracing will be provided at bottom level of wall frames to prevent deformation at lifting time. Plan of buildings is rectangle (30'x25') and staircase is installed separately too.
Does anybody have experiences or suggestion for mentioned method of construction?