Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Inflated resources in Primavera P6.1

Status
Not open for further replies.

TGHoesch

Mechanical
Feb 15, 2013
1
I'm working with P6.1 and I'm running into an issue where resources imported into the schedule from another scheduler are inflated. This only occurs with hourly resources (quantities maintain their values). Also when the schedule is exported and imported by the other scheduler the values import to the other computer correctly. If anyone has any insight on which setting may be causing this I would greatly appreciate it.

Thanks in advance.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor