Motorspirit
Petroleum
- Jul 22, 2009
- 24
Hi all
I have a tank structure (with four legs) that needs to be anchored to an existing concrete slab. The chemically fixed anchors I want to use require a min embedment depth of 300mm. I can only get 200mm embedment out of the existing slab.
I can pour local footings/plinths on top of the existing slab, one under each leg, to increase my embedment depth. I can make these large enough, in plan, to accommodate the theoretical projected area of a cone pull out failure.
Question is, if I simply scabble the existing surface and pour a new concrete footing on top, will the two act as one (ie as if it had all been poured at the same time) in terms of a cone pull out failure? Or should I add extra steel reinforcement to "dowel" the new slab into the existing to prevent the top one trying to prematurely lift away from the bottom in the even of cone out type failure.
The extra plinths Im considering would have dimensions of 1500mm x 1500mm x 100mm thk.
Appreciate any thoughts
Thanks
I have a tank structure (with four legs) that needs to be anchored to an existing concrete slab. The chemically fixed anchors I want to use require a min embedment depth of 300mm. I can only get 200mm embedment out of the existing slab.
I can pour local footings/plinths on top of the existing slab, one under each leg, to increase my embedment depth. I can make these large enough, in plan, to accommodate the theoretical projected area of a cone pull out failure.
Question is, if I simply scabble the existing surface and pour a new concrete footing on top, will the two act as one (ie as if it had all been poured at the same time) in terms of a cone pull out failure? Or should I add extra steel reinforcement to "dowel" the new slab into the existing to prevent the top one trying to prematurely lift away from the bottom in the even of cone out type failure.
The extra plinths Im considering would have dimensions of 1500mm x 1500mm x 100mm thk.
Appreciate any thoughts
Thanks