moondoggy
Mechanical
- Feb 7, 2005
- 11
We have a room in our building that houses two silos used to store soybeans. In addition, there are bucket elevators used to move the material to the processing area located in another room. All of the equipment and silos have dust collection pickups on them which convey any dust to outdoor located baghouses. Our engineer did not rate the area, but the local building inspection authority is maintaining that this area should have been rated an H2.
Our engineer calculated dust generation to be below 12 lbs, which in accordance with the 1996 IBC was considered exempt from the H2 rating. Anything below 125 lbs. (in the 1996 edition) was considered to be exempt. However, in the IBC 2000, we are told that dust had been removed from Table 307.7 and therefore no further exemptions for the quantity of dust are allowed. But our engineer maintains that the remaining category of flammable solids still would apply for dust in Table 307.7 and therefore the exemption should still be allowed.
We are deadlocked on both sides. Meanwhile our building cannot receive its CO and our client is screaming that they cannot get into production. Our facility is 100% built with this one issue holding up the Building CO.
Can anyone lend some insight into this issue and how to go about defending our engineers position. We need to move this along quickly and feel that some additional insight as to the intention behind eliminating the dust category from the 2000 IBC would help move this along.
Our engineer calculated dust generation to be below 12 lbs, which in accordance with the 1996 IBC was considered exempt from the H2 rating. Anything below 125 lbs. (in the 1996 edition) was considered to be exempt. However, in the IBC 2000, we are told that dust had been removed from Table 307.7 and therefore no further exemptions for the quantity of dust are allowed. But our engineer maintains that the remaining category of flammable solids still would apply for dust in Table 307.7 and therefore the exemption should still be allowed.
We are deadlocked on both sides. Meanwhile our building cannot receive its CO and our client is screaming that they cannot get into production. Our facility is 100% built with this one issue holding up the Building CO.
Can anyone lend some insight into this issue and how to go about defending our engineers position. We need to move this along quickly and feel that some additional insight as to the intention behind eliminating the dust category from the 2000 IBC would help move this along.