I have a 3.6m internal diameter bolted concrete segmental tunnel enter

Status
Not open for further replies.

Ginger

New member
Joined
May 8, 1999
Messages
284
Location
GB
I have a 3.6m internal diameter bolted concrete segmental tunnel entering a circular shaft of 12.5mID. The tunnel turns through 120 degrees on plan before exiting the shaft. To form this circular curve in the tunnel I intend to cast an in-situ concrete block arount a 3.6mID curved former in order to maintain the correct tunnel cross section. Has anyone done something similar? Is the formwork best constructed of timber or a fabricated steel tube, or GRP to form a permanent formwork? The tunnel is to carry sewage. Any thoughts gratefully received.<br>
Thanks<br>
Ginger
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top