Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

I have a 3.6m internal diameter bolted concrete segmental tunnel enter

Status
Not open for further replies.

Ginger

New member
May 8, 1999
284
I have a 3.6m internal diameter bolted concrete segmental tunnel entering a circular shaft of 12.5mID. The tunnel turns through 120 degrees on plan before exiting the shaft. To form this circular curve in the tunnel I intend to cast an in-situ concrete block arount a 3.6mID curved former in order to maintain the correct tunnel cross section. Has anyone done something similar? Is the formwork best constructed of timber or a fabricated steel tube, or GRP to form a permanent formwork? The tunnel is to carry sewage. Any thoughts gratefully received.<br>
Thanks<br>
Ginger
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor