Yea, after thanking it through I came to the same conclusion. How ever, the HRSG’s are Nooter/Eriksen with only 1 DA tank over the LP drum, using 2 100% BFW pumps supplying only 1 HRSG. From a bid stand point it would be nice if the HRSG maf. would provide a GA drawing showing the amount of FW remaining in the erection of the unit. Example, if in 10 spool pieces you have 5 shop welds based on the connection points listed in the drawing you will have 4 tie in welds or field welds. There is no quick way to determine this with out going over all the drawings and counting all the welds. This project will have around 6000 welds.