I very urgently need an advice on how to establish an updating process with Primavera.
Do you have any step by step procedure to update the schedule?
For example:
1. Step: Activate the “Progress Spotlight”
2. Step: Go to “Tools” - “Update Progress” and click “Apply”
3. Step: Enter the “Remaining Duration”
4. Step: Go to “Tools” - “Apply Actuals”
My problem:
When do I have to do what (what is a good sequence to get good results)? For example when do I have to enter the new “Data Date”?
My premises are the following:
• The “% Complete Type of all activities is “Duration”.
• I don’t have any resources assigned. (So I don’t need to update any resources. Makes things easier, doesn’t it?)
• I just have to update the actual dates.
• I need to get the variances of dates and durations.
I’m looking forward to your answers! Thanks in advance for your help.
I very urgently need an advice on how to establish an updating process with Primavera.
Do you have any step by step procedure to update the schedule?
For example:
1. Step: Activate the “Progress Spotlight”
2. Step: Go to “Tools” - “Update Progress” and click “Apply”
3. Step: Enter the “Remaining Duration”
4. Step: Go to “Tools” - “Apply Actuals”
My problem:
When do I have to do what (what is a good sequence to get good results)? For example when do I have to enter the new “Data Date”?
My premises are the following:
• The “% Complete Type of all activities is “Duration”.
• I don’t have any resources assigned. (So I don’t need to update any resources. Makes things easier, doesn’t it?)
• I just have to update the actual dates.
• I need to get the variances of dates and durations.
I’m looking forward to your answers! Thanks in advance for your help.