Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations The Obturator on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Hooked Bar Development Length Side Cover and Top or Bottom Cover

Status
Not open for further replies.

Quade999

Civil/Environmental
May 29, 2020
61
Hello Everyone,

For the calculation of a hooked bars development length, all the codes have a stipulation that if at a discontinuous end with both side cover and top or bottom cover less than 2.5 inches, then ties or stirrups are required along the hook.

Code_1_pnkiua.png

Code_2_svbbw5.png


My understanding is that when they say "both" it means that the the side cover and the top cover need to simultaneously be less than 2.5 inches for this to apply, and not "both" as in an either or type of situation, where only one of them needs be less than 2.5 inches.
i.e. that my side cover can be 2 inches and my top cover can be 2.5 inches, or my side cover can be 2.5 inches and my top cover can be 2 inches, and ties will not be required as per the clause. Is this understanding correct?

Thanks.
 
Replies continue below

Recommended for you

I agree with your interpretation, as the conjunction "and" in between the two conditions means "if both are true, then", otherwise it shall state "either..or..", then only one condition needs to be met. However, for what reason your beam will ends up like this?
 
Like retired13, I question why you need to develop those bars. Is there a large point load, say a column, supported on the end of the cantilever?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor