jtseng123
Mechanical
- Jun 6, 2012
- 530
Dear all,
I have an acid gas knock drum 5' dia x 12' T/T vertical, which our process classifies as lethal service. It is 316/316L SS construction.
Per code lethal service requires PWHT. My question is, shall I ask for solution anneal after fabrication ?
(I have vendors either will provide solution anneal on base metal only, or no bid because of the concern of deformation or does not have enough water storage for quenching the entire vessel.)
I have an acid gas knock drum 5' dia x 12' T/T vertical, which our process classifies as lethal service. It is 316/316L SS construction.
Per code lethal service requires PWHT. My question is, shall I ask for solution anneal after fabrication ?
(I have vendors either will provide solution anneal on base metal only, or no bid because of the concern of deformation or does not have enough water storage for quenching the entire vessel.)