DCHAZEN
Civil/Environmental
- Sep 26, 2009
- 5
BACKGROUND:
We are in the early stages of construction of a design build power plant in Southern California. Part of the project includes a small bridge with drilled caissons supporting the abutments. In the area where the caissons are to be installed the geotechnical report shows that augers were refused at 2.5' below grade. The boring logs also show that gabbro and dark dioritic cobbles with sitly to clayey fine to coarse sand were the majority soil components. The caissons are also directly adjacent to a protected water way and the geometery of the site eliminates the possiblity of using pile driving equipment- the caissons must be drilled.
The caisson design calls for a 24" steel cassing with rebar welded to the inside of the top 5' of the cassing to connect it to the bridge abutment.
The caissing will then be filled with 4500 PSI concrete. The design also calls for an epoxy coating on the top 5' of the caisson to resist corresive properties of the top soil.
THE PROBLEM:
The drilling subcontractor cannot install a 24" cassing in a hole drilled with their 24" auger because the large amount of cobbles in the soil will result in a hole smaller than 24" at multiple depths and locations throughout the bore.
They propose to drill a 30" hole, install the 24" cassing, and grout or concrete around the outside as well as inside of the cassing after installation.
The geotechnical engineer does not like this solution because he believes that it will signifigantly decrease the skin friction and therefore the bearing capacity of the pile.
Additionally it was suggested to weld rebar to the outside of the cassing to increase skin friction- this solution is still being evaluated.
QUESTIONS TO THE FORUM:
Any ideas or solutions to consider?
As a young engineer I do not understand how concreting or grouting outside the cassing could decrease the skin friction- the cassing will be bearing against almost exclusively rock and I would think concrete would increase contact area between the rock and cassing increasing skin friction. Help me to understand this mechanism.
Also- this is beside the point because the current design must be made to work- but I would think this would have been an excellent application for an auger cast pile. Just for my general knowledge any other design ideas would be appreciated.
Thanks
We are in the early stages of construction of a design build power plant in Southern California. Part of the project includes a small bridge with drilled caissons supporting the abutments. In the area where the caissons are to be installed the geotechnical report shows that augers were refused at 2.5' below grade. The boring logs also show that gabbro and dark dioritic cobbles with sitly to clayey fine to coarse sand were the majority soil components. The caissons are also directly adjacent to a protected water way and the geometery of the site eliminates the possiblity of using pile driving equipment- the caissons must be drilled.
The caisson design calls for a 24" steel cassing with rebar welded to the inside of the top 5' of the cassing to connect it to the bridge abutment.
The caissing will then be filled with 4500 PSI concrete. The design also calls for an epoxy coating on the top 5' of the caisson to resist corresive properties of the top soil.
THE PROBLEM:
The drilling subcontractor cannot install a 24" cassing in a hole drilled with their 24" auger because the large amount of cobbles in the soil will result in a hole smaller than 24" at multiple depths and locations throughout the bore.
They propose to drill a 30" hole, install the 24" cassing, and grout or concrete around the outside as well as inside of the cassing after installation.
The geotechnical engineer does not like this solution because he believes that it will signifigantly decrease the skin friction and therefore the bearing capacity of the pile.
Additionally it was suggested to weld rebar to the outside of the cassing to increase skin friction- this solution is still being evaluated.
QUESTIONS TO THE FORUM:
Any ideas or solutions to consider?
As a young engineer I do not understand how concreting or grouting outside the cassing could decrease the skin friction- the cassing will be bearing against almost exclusively rock and I would think concrete would increase contact area between the rock and cassing increasing skin friction. Help me to understand this mechanism.
Also- this is beside the point because the current design must be made to work- but I would think this would have been an excellent application for an auger cast pile. Just for my general knowledge any other design ideas would be appreciated.
Thanks