Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Extended Days

Status
Not open for further replies.

PRDIGM

Mechanical
Aug 9, 2007
2
In MS Project durations for activities which are not resource dependent (such as preheating a furnace) can be entered as 'e' days(6e). How we do it in Suretrak or P3?
 
Replies continue below

Recommended for you

Thanks but I solved it by creating a 24-7 calendar and assigning it to the activity. That way activities that don't depend upon resourcing such as concrete curing, filling a reservoir with water, emptying a tank, drying out a newly insulated furnace etc. can be calculated using the correct duration.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor