Hgcdesign:
Funny thing about this thread, and your actions…, you are the builder (or GC) not the Engineer (EOR) who signed the plans and who was the person the owner hired to design the building to the local bldg. code, for permitting, etc. We can spend days guessing at what really happened, based on a fairly half a$$ed explanation of the facts, and we still won’t turn you into an engineer, so that you undertake and assume the EOR’s responsibility and liabilities. Didn’t anyone ever suggest to you that you ‘FOLLOW THE DAMN PLANS,’ and then you are in the clear if anything goes wrong. If you want to make alterations or changes, you should clear these changes with the engineer, so there is no question later. Build your case, show your savings or improvements to the engineer with a complete and intelligent explanation and pass the saving on to the owner, not into your own pockets, and usually you should be well received.
Either you or the stl. supplier deviated from the plans without pre-approval, and you didn’t check the shop drawings, or didn’t bother to request any shop drawings, so this bull lies with you. There usually is a reason for some concern about the first interior post/ftg. loads for the scenario that you presented, although in this case, for these light loads and small spans adjustments probably could have been made, with a diplomatic approach to the engineer. If 24” sq. ftgs. where o.k. under two 25’ long 2 span continuous beams each 12.5’-12.5’ span lengths, center splice over a column, and 12.5’-12.5’, the worst post load would already have been contemplated and covered. Undoubtedly, the engineer’s thinking for the two 25’ beams was transport and site handling of the full length beam, not to spite you or the stl. guy. What about the change in TJI’s, is the floor elev. now 2” higher or did they loose 2” in clg. height? Does this cause interference with any mechanicals, before they get there with their chain saws, and who fixes and coordinates all this?
It is not uncommon for the engineering office to send out young engineers on what should be fairly simple inspections (construction observations). They are usually not experienced enough to make changes on the fly, so they will tend to follow the plans, and call you on deviations from the plans. There is usually no sense in arguing with them, nor should it be taken as disrespecting them when you go to their boss to try to iron things out. But, don’t assume they were disrespecting you either for asking you to follow the plans, plans and specs. aren’t called ‘the construction suggestions for a reason.’