TPWells
Civil/Environmental
- Jun 20, 2013
- 4
Hi,
I am designed a concrete basin for a cooling tower which is 20m x 10m in plan dimension. The base is made up of a 500mm thick slab sat on a number of ground beams on piles. In the design of the base slab I have allowed for early thermal cracking as per BS 8007 and due to the piles have included an end restraint factor of 0.5 [which is assuming the slab is restrained at each end]. At the moment I am tying in the pile caps to the base slab with rebar. As per BS 8007 it says I have to take into account the restraining factor of the piles. Would using a 0.5 restraining factor be adequate to take this into account?
Thanks,
Tim
I am designed a concrete basin for a cooling tower which is 20m x 10m in plan dimension. The base is made up of a 500mm thick slab sat on a number of ground beams on piles. In the design of the base slab I have allowed for early thermal cracking as per BS 8007 and due to the piles have included an end restraint factor of 0.5 [which is assuming the slab is restrained at each end]. At the moment I am tying in the pile caps to the base slab with rebar. As per BS 8007 it says I have to take into account the restraining factor of the piles. Would using a 0.5 restraining factor be adequate to take this into account?
Thanks,
Tim