ACI 360 recommends sawcutting to 1/3 of the slab depth for control joints in steel fibre reinforced slab on grade.
Does anyone know of an ACI or PCA publication that gives a recommendation for depth of sawcut in steel fibre reinforced slab on grade if an early entry saw is used?
Does anyone know of an ACI or PCA publication that gives a recommendation for depth of sawcut in steel fibre reinforced slab on grade if an early entry saw is used?