Duration , start and end time in hours.

Status
Not open for further replies.

devagupt

Industrial
Nov 20, 2007
6
US
Hello

How would i change the duration of tasks in a project file to hours so that the duration , the start and end time would appear in hours.

Please help!

Thanks in advance.
 
Replies continue below

Recommended for you

Good question. Assuming you are talking about an active / already built MS Project schedule, there are a few things you will need to do:

1. To change Start and Finish to show Hours: click on >Tools, >Options, >View, click on the dropdown for Date Format and change to 12:33PM and click on OK.


2. To change Duration to show hours: Click on >Tools, >Options, >Schedule and change the option “Duration is entered in” to Hours

This article will show screenshots for steps 1 and 2:

3. You will notice step 2 did not change the Duration format for any existing tasks. This article will show you exactly how to do that:

Hope this helps!