Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Drawing for Top level assembly

Status
Not open for further replies.

ashivu123

Aerospace
Joined
Oct 24, 2013
Messages
153
Location
US
we are facing problem with placing the views in dafting in TOP level seat assembly that contains around 2600 parts. Takes lot of time to create views and update views in drawing dataset.

1. loaded assembly with lightweight and created exploded view while placing the views selected option in general tab lightweight. This option worked faster, however unable to pick the hole surfaces for trace line and also edges are not selecting in drafting for view dependent edit or to extract curve.

2. loaded assembly with normal load option created exploded view and trace line, while placing view in drawing sheet selected lightweight in view style before placing the views. This takes just less time compared to normal view placement.

Let me know is their best method for top level drawing creation to reduce time