I think I am explaining poorly. My situation is that a building is being expanded over an existing sanitary line. Obviously, we plan to lay new pipe outside of the building envelope. Where the new pipe intersects the existing pipe we will use doghouse manholes. My question relates to the order in which construction occurs.
I will construct upstream doghouse manhole with existing active line running through manhole to service upstream users. Then, I will lay new pipe down to downstream intersection and construct another doghouse mahhole. When I break active line to redirect flow through new pipe, the existing pipe entrance through the doghouse manhole will be open, allowing flow through existing pipe. How do you deal with this? Hope this makes sense.