hugop973
Electrical
- Oct 1, 2008
- 16
Is there a minimum separation recommended between a Data Center and a 115KV Substation. The Ground Potential Rise in an existing Data Center adjacent to a 115KV substation (wall to wall) is 809V, there's a concern about the EMI affecting the performance of the servers, routers, etc.
GPR of 809V is considered acceptable or high?
Any technical paper, report or investigation that can be used as a reference?
Thanks for your help
GPR of 809V is considered acceptable or high?
Any technical paper, report or investigation that can be used as a reference?
Thanks for your help