pricklyPete
Structural
- May 14, 2004
- 25
I have a 12" thick slab with #5 @12" o.c top and bottom. I want the steel to be continuous through the control joints (and construction joints). I read somewhere that the control joint should be cut to a depth of 1/3 the slab thickness. If I have top steel with 2" of cover, they will not be able to cut the joint any deeper than 2".
The slab is for a water tank that will probably be leak tested. There will be no membrane on the tank floor during this test.
Does anyone have any suggestions? The tank is 70'x70'
The slab is for a water tank that will probably be leak tested. There will be no membrane on the tank floor during this test.
Does anyone have any suggestions? The tank is 70'x70'