The crushing plant is classified as non-hazardous and is located on a tropic climate with medium to high humidity. We have complied with the local code on providing drainage to lowest part of conduits by providing "Tee" condulet junction box + reducer + 1/2" drain fitting on the lowest portion of each conduit run.
However, one designer suggested to use a Tee condulet junction box instead and let the lower side of the junction box open so as to act as drain. The crushing plant is dusty and somehow we have concerns that the junction box opening to large enough for dust or rodents/inspects to enter.
Is the designer suggestion acceptable or our Reducer+drain fitting better? I would appreciate anyone who encountered the same installation offer their comments and recommendations.
However, one designer suggested to use a Tee condulet junction box instead and let the lower side of the junction box open so as to act as drain. The crushing plant is dusty and somehow we have concerns that the junction box opening to large enough for dust or rodents/inspects to enter.
Is the designer suggestion acceptable or our Reducer+drain fitting better? I would appreciate anyone who encountered the same installation offer their comments and recommendations.