rowingengineer
Structural
- Jun 18, 2009
- 2,468
I am told that the sawn joint detail with the reinforcement continuous is out of date (first detail in the PFD). Apparently the second detail should be adopted as the standard.
I am told everyone does the second detail in the PDF these days. However I have been using the first detail for years and never had any more problems with it then I do with the second detail. I have also worked at four practices that have used the first detail as standard.
So what I would like to know is what your standard sawn joint or tool joint detail. Do you still use number one or are you using number two and WHY?
Arguing with an engineer is like wrestling with a pig in mud. After a while you realize that they like it
I am told everyone does the second detail in the PDF these days. However I have been using the first detail for years and never had any more problems with it then I do with the second detail. I have also worked at four practices that have used the first detail as standard.
So what I would like to know is what your standard sawn joint or tool joint detail. Do you still use number one or are you using number two and WHY?
Arguing with an engineer is like wrestling with a pig in mud. After a while you realize that they like it