martin888888
Civil/Environmental
- Jun 15, 2010
- 157
We have a small (150ft) length of roadway that is being used as a wet crossing. It is a 12" culvert will the 150ft length of concrete driveway pured over top of it. We want to raise this roadway max 2' and install 2-15" culverts. Before concrete is poured on old concrete is a bonding agent normally needed?