struct_eeyore
Structural
Hi all,
I have recently been asked to verify a generator footing - it was designed/poured without engineering and county rejected it. Unfortunately, the footing was not sized for overturning - need 37k-ft for 1.6 factor, and deadload of generator and footing only provide 18k-ft. However, the footing actually rests on an existing 6" concrete slab and poured adjacent to another pad. So this might be far-fetched, but I am wondering if it is legitimate to assume that on the end of the footing that is poured tight, assuming there is no sliding, a couple is formed to prevent overturning (as in a piece of concrete would have to be sheared off to allow the vertical edge to lift up past another vertical edge, or alternatively, get crushed to go the other way. And as gravy on top, I am also wondering if I could use some values for concrete adhesion to provide some tension to the free edge of footing.
Thanks
-G.S.
I have recently been asked to verify a generator footing - it was designed/poured without engineering and county rejected it. Unfortunately, the footing was not sized for overturning - need 37k-ft for 1.6 factor, and deadload of generator and footing only provide 18k-ft. However, the footing actually rests on an existing 6" concrete slab and poured adjacent to another pad. So this might be far-fetched, but I am wondering if it is legitimate to assume that on the end of the footing that is poured tight, assuming there is no sliding, a couple is formed to prevent overturning (as in a piece of concrete would have to be sheared off to allow the vertical edge to lift up past another vertical edge, or alternatively, get crushed to go the other way. And as gravy on top, I am also wondering if I could use some values for concrete adhesion to provide some tension to the free edge of footing.
Thanks
-G.S.