We have a description of a processing bay with a vinyl tile covered concrete floor stating the bay floor has a load limit of 2000 PSF.
The customer wants to bring in a dolly that weighs 24,000 LBS loaded.
The dolly is on casters, and we don't know if there are 6 or 4 casters on the dolly.
Do we need to place steel sheets under the casters to prevent damage to the floor?
Any guidance would be appreciated
The customer wants to bring in a dolly that weighs 24,000 LBS loaded.
The dolly is on casters, and we don't know if there are 6 or 4 casters on the dolly.
Do we need to place steel sheets under the casters to prevent damage to the floor?
Any guidance would be appreciated