Hi everyone,
I have a situation where I have to frame a 48” deep beam to a 24” deep beam. I’m not sure what to do with the 48” beam’s bottom bars. Since there is only negative moment at the interface, should I just develop the top bars of the 48” beam into the 24” beam? For the bottom bars of the 48” beam, do I also need to develop them to the 24” beam or they can just have a standard hook end?
Thanks in advance.
Jay
I have a situation where I have to frame a 48” deep beam to a 24” deep beam. I’m not sure what to do with the 48” beam’s bottom bars. Since there is only negative moment at the interface, should I just develop the top bars of the 48” beam into the 24” beam? For the bottom bars of the 48” beam, do I also need to develop them to the 24” beam or they can just have a standard hook end?
Thanks in advance.
Jay