wildehond
Structural
- Mar 24, 2006
- 54
When designing RC columns that start at foundation level, do you increase the cover for the reinforcing below ground? And then change it higer up only? Is it an option to investigate the the cost effectivenes of using some specialist cover enhancer to the sections of reinf below ground and in this way keep the cover consistant?