Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations 3DDave on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Concrete Balcony Detailing Practice 3

Status
Not open for further replies.

bookowski

Structural
Aug 29, 2010
983
Question regarding standard practice for durability of concrete cantilever balconies per ACI318.

I am talking about cantilever cast in place concrete, with at a minimum some type of surface applied finish/waterproofing and in some cases a raised surface (pavers etc.).

My interpretation of ACI would be that this is not 'exposed to weather' based on the commentary explanation of the intent being 'direct exposure to moisture changes..... wetting, drying etc.', essentially this is similar to a waterproofed roof. This implies 3/4" cover. Based on chapter 4 exposure categories it looks like the only requirement would be 0.45 w/c ratio, no increased cover.

The above would imply that it is sufficient to use 3/4" cover, W/C <= 0.45, and air entrainment. Is this standard practice? Knowing that balconies very often have corrosion issues eventually I am tempted to increase cover as added protection. Increasing cover to say 1.5" however has a decent impact on what kind of cantilever I can achieve (due to reduced 'd') and to stay competitive I don't want to be too conservative. Another option is epoxy coated bars but I'm not a huge fan.
 
Replies continue below

Recommended for you

Yes, the bars should be stopped short of the drip groove. That obviously wasn't done in the photos which Trenno attached.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor