JAYDEE23
Materials
- Jun 16, 2009
- 146
Guys please help direct me.
We are remaking an old B31.1 pipe section that had the following configuration on the sampling tap.
90 degree welded WYE 2" Sch 40S 317SS (made from 3 pipes)
welded to
4" Sch40S 317SS Header pipe.
I am good with the Header and Branch Min wall thickness and reinforcement calcs.
I cannot for the life of me find any direction on equations for a WYE.
I see the forged WYE are all proofed by FEA or Burst test.
Anyone know if there is any "by paper" design equations for wall thickness requirements/reinforcement for welding 3 pipes together to make a WYE?
I will likely go with the forged purchased WYE, although ridiculously expensive, but I am curious to know if there is any design guidance out there for making a WYE from pipe.
We are remaking an old B31.1 pipe section that had the following configuration on the sampling tap.
90 degree welded WYE 2" Sch 40S 317SS (made from 3 pipes)
welded to
4" Sch40S 317SS Header pipe.
I am good with the Header and Branch Min wall thickness and reinforcement calcs.
I cannot for the life of me find any direction on equations for a WYE.
I see the forged WYE are all proofed by FEA or Burst test.
Anyone know if there is any "by paper" design equations for wall thickness requirements/reinforcement for welding 3 pipes together to make a WYE?
I will likely go with the forged purchased WYE, although ridiculously expensive, but I am curious to know if there is any design guidance out there for making a WYE from pipe.