My Client has requested a bolt-tightening sequence to be included in the installation guidelines document for an Offshore Flexible Riser 2-piece Hang-off Clamp which has a horizontal circular PCD bolt group and a vertical rectangular bolt group.
Do Engineers usually just specify 3-stage spiral sequence (just like most car engine head-bolts)or is there some kind of calc I should be doing??
Do Engineers usually just specify 3-stage spiral sequence (just like most car engine head-bolts)or is there some kind of calc I should be doing??