Yes, be glad to. You, or someone in your organization (YOSIYO), needs to read the relevant material specifications. YOSIYO needs determine if the materail offered by the supplier is indeed equivalent to the desired material.
YOSIYO needs to decide if the CSA material is equivalent to the ASTM material noted on the MTR. YOSIYO needs to determine if the CSA materail is noted on the MTR as well.
YOSIYO needs to read the relevant project documents to determine if any substitution of materials is permitted. YOSIYO most likely needs to contact the buyer or eventual owner to determine if such substitutions are acceptable.
Then you, or someone in your organizatipon, will know what to do.
It's a slog, but it's the only real way.
Regards,
Mike
The problem with sloppy work is that the supply FAR EXCEEDS the demand