rmillercwi
Materials
- Jul 19, 2006
- 76
I have a spool section of 6" 2.25 cr pipe with a non pressure part welded to a pressure part (in the shop, under an S stamp) being sent out to the field for installation in an existing boiler that has been running for years. (NBIC applys)
Its simply a fillet welded donut welded inside a pipe basically working as a restrictor plate. The pipe is beveled on both ends ready for the guys in the field to install. Cut out old pipe, replace with new pipe.
ASME section 1 pw-54 says non pressure parts welded to pressure parts are exempt from hydro test if the material is carbon steel and the weld is looked at by the AI. This pipe is not carbon steel therefore it appears this spool section must by hydrotested to Sect 1
It also says the hydro can be done either in the shop or the field. If we choose to hydro in the field can we use NBIC rules regarding test pressure (or the lack of it entirely if using some other method such as NDE)
It appears to me this spool section requires a 1.5 x hydro pressure wittnessed by the AI no matter what.
Correct?
Its simply a fillet welded donut welded inside a pipe basically working as a restrictor plate. The pipe is beveled on both ends ready for the guys in the field to install. Cut out old pipe, replace with new pipe.
ASME section 1 pw-54 says non pressure parts welded to pressure parts are exempt from hydro test if the material is carbon steel and the weld is looked at by the AI. This pipe is not carbon steel therefore it appears this spool section must by hydrotested to Sect 1
It also says the hydro can be done either in the shop or the field. If we choose to hydro in the field can we use NBIC rules regarding test pressure (or the lack of it entirely if using some other method such as NDE)
It appears to me this spool section requires a 1.5 x hydro pressure wittnessed by the AI no matter what.
Correct?