Hi gents
let us say that i am preparing a contractual documents, and the list of scope of work. one of the list Items is welding
I wrote: Welding of all pipes connection as per ASME B31.3 and AWS 1-1.
my question is:
1 st: Is the contractor must do the welding including NDE either (UT, RT)
(I will not mention any NDE or NDT in the scope of work)
2nd if NDE not included, if the welding done as per AWS or ASME B31.3 that means will be no welding points will be defected? correct me if wrong
what I am looking for is the procedure of welding on ASME B31.3 or AWS can ensure there will be not failure in welding points after NDE?
the material of the pipes is A53 grade B size (2" to 8")
let us say that i am preparing a contractual documents, and the list of scope of work. one of the list Items is welding
I wrote: Welding of all pipes connection as per ASME B31.3 and AWS 1-1.
my question is:
1 st: Is the contractor must do the welding including NDE either (UT, RT)
(I will not mention any NDE or NDT in the scope of work)
2nd if NDE not included, if the welding done as per AWS or ASME B31.3 that means will be no welding points will be defected? correct me if wrong
what I am looking for is the procedure of welding on ASME B31.3 or AWS can ensure there will be not failure in welding points after NDE?
the material of the pipes is A53 grade B size (2" to 8")