PINOLERO
Industrial
- Jul 14, 2010
- 7
Hi Everybody:
Could anyone help me with the following doubt?:
We just finished to build a 5,000m3 API 650 tank. We are planning the hydrostatic test, however, we are not installed the firefighting pipeline which will be supported on the tank shell. We neither installed the datum plate at bottom of the tank. Can we do the hydrostatic test even though we are going to do further welding jobs at the tank shell and bottom after this test?.
Thank in advance for your help
Best Regards,
Could anyone help me with the following doubt?:
We just finished to build a 5,000m3 API 650 tank. We are planning the hydrostatic test, however, we are not installed the firefighting pipeline which will be supported on the tank shell. We neither installed the datum plate at bottom of the tank. Can we do the hydrostatic test even though we are going to do further welding jobs at the tank shell and bottom after this test?.
Thank in advance for your help
Best Regards,