Hai,
Here i was reviewed the XXXX MTC for API 5L Grade B they not mentioned the PSL 1 or PSL 2 in MTC. So i have to request the supplier to revise the MTC. My client not asked about this. But i have doubt its mandatory it should be mentioned?
REGARDS,
G.SRIRAM.