F1955
Structural
- Oct 27, 2003
- 22
I have a base plate on a concrete pier with #8 bars & 1" bolts in the base plate. Does anyone have literature as far as the best way to calculate required development length of the anchor bolts? Would you develop the vertical bars? Would you use the 160 psi bond strength to figure development length? I know some people who develop the vertical bars & end up with anchor bolts 24"-36". Thank you for you comments.